Question 1

A business analyst has started a project for a system enhancement. In order to determine how the
requirements will be approved, the business analyst schedules a meeting with the stakeholders to discuss
the proposed approval process.
Which measure of effective decision making allows the business analyst to finalize the process for
requirement approval?


Answer: A
Question 2

A project was in the design phase when the team received news of a new regulatory mandate that affects
the project. The requirements have already been approved and baselined. If the new requirements are not
included, the company will be out of compliance and may face monetary penalties.
What should the business analyst do next?


Answer: C
Question 3

The business analyst is planning an approach to formally manage updates to requirements that may be
requested by stakeholders. What should the business analyst do?


Answer: C
Question 4

The business analyst wants to ensure that requirement changes can be formally tracked after the product is baselined. What will the business analyst need to evaluate the proposed change? 


Answer: B
Question 5

Requirements elicitation for a project is occurring. The marketing, acquisition, and production departments
want to include specific requirements. The CEO has a requirement to deploy in three months.
Which of the following actions will have a greater influence on the project success?


Answer: C
Page:    1 / 41      
Total 205 Questions | Updated On: May 22, 2026
Add To Cart

© Copyrights TheExamsLabs 2026. All Rights Reserved

We use cookies to ensure your best experience. So we hope you are happy to receive all cookies on the TheExamsLabs.